Use this page to select your project and define the file or database connection that contains the actual cost records for importing data.
Note: If you are importing data that contains quotes in the descriptions, you must use the XLS format of the file. You must also select the
File contains a header row option on the Field Mapper page.
Contents
Field | Description |
Project
|
Use this field to define the project where the actual costs will be imported. Click
to select a project or master project.
Note: Only projects where you have right access are displayed.
|
Actual cost file
|
Select this option if you are importing actual cost records from a file. Click
to locate the file.
|
Connection name
|
Select this option if you are importing actual costs records from a database. Click
New to create a new connection using the New Connection dialog box or
Edit to modify an existing connection using the Edit Connection dialog box.
Note: Selecting this option displays the Database Table Selection page after you click
Next.
|
Actual cost file contains records at the following level
|
Use this field to define the level of costs contained in the actual file. Select one of the following options from this drop-down list:
- Control Account Prompt
- Work Package Prompt
Note: This field is enabled only if the project has actual costs defined at both levels; otherwise, the level of the project is selected and the field is disabled.
|